Difference between revisions of "Campus Infrastructure"
(Created page with "Campus Infrastructure is the software and hardware that CNMCyber Team rents from Hetzner to host CNM Campus Farm. The rented software and hardware consists of...") |
|||
Line 1: | Line 1: | ||
− | [[Campus Infrastructure]] is the software and hardware that [[CNMCyber Team]] rents from [[Hetzner]] to host [[CNM Campus Farm]]. The rented software and hardware consists of [[#]]. Both are parts of [[Opplet Infrastructure]]. | + | [[Campus Infrastructure]] (hereinafter, [[#The Infra]]) is the software and hardware that [[CNMCyber Team]] rents from [[Hetzner]] to host [[CNM Campus Farm]]. The rented software and hardware consists of [[#]]. Both are parts of [[Opplet Infrastructure]]. |
Revision as of 17:43, 10 December 2023
Campus Infrastructure (hereinafter, #The Infra) is the software and hardware that CNMCyber Team rents from Hetzner to host CNM Campus Farm. The rented software and hardware consists of #. Both are parts of Opplet Infrastructure.
Contents
Provider and costs
The Provider
- For the purposes of this very wikipage, the Provider refers to Contabo, which has been serving as #The Team's Internet service provider (ISP) and lessor of both #The Infra and Bureau Infrastructure since 2016. Offers from other potential providers, specifically, Contabo and DigitalOcean, have been periodically reviewed, but no one else has offered any better quality/price rate on a long-term basis.
Costs
Category Product Description Quantity Unit Price Price (excl. VAT) Servers Server Auction #1846134 1 38.5 38.5 Primary IPv4 Server #1846134 1 1.7 1.7
Requirements
Due to the lower cost, #The Metal's rentals were purchased via #The Provider's auction -- https://www.hetzner.com/sb?hdd_from=500&hdd_to=1000 -- based on the following assumptions.
Number of nodes
- ProxmoxVE normally requires three nodes. The third node is needed to provide quorum; however, it shall not necessarily run applications. At the same time, Ceph's non-emergency operations require three nodes at least.
Hard drives
- The hard drive storage capacity for any of #The Nodes shall be 512Gb at least.
- Because Ceph is selected to power #The Storage, any hard-drive of #The Metal shall be both SSD and NVMe.
Processors
- The processor frequency for two Nodes of #The Metal shall be 32Gb at least. Processor frequency requirements to the third of #The Nodes may be lower because of ProxmoxVE's characteristics.
- Those servers that deploys Intel Xeon E3-1275v5 processors are preferable over those servers that deploys Intel Core i7-7700 ones.
Location
- At least two Nodes shall be located in the same data center. Although #The Provider does not charge for internal traffic, this circumstance increases the speed of #The Farm as a whole. If no nodes are available in the same data center, they shall be looked for in the same geographic location.
The UI
With regards to #User interfaces (UIs), administrative access to #The Metal can be accomplished through several tools and portals that #The Provider grants to CNMCyber Customer.
GI
- Its graphic interface belongs to #Dashboards.
CLI
- For the purposes of this very wikipage, a command line refers to a command line interface (CLI) of any of #The COTS packages installed in #The Farm. This input-output line area allows #The Sysadmins and #The Superusers to interact with #The Cluster and #The Infrastructure rather than screen-based graphical buttons, icons, or hyperlinked texts in graphic user interfaces (GUIs).
The Metal
#The Habitat is deployed on three bare-metal servers and one storage box. As the result of #Choosing the metal, #1736579, #1777698, #2109682, and #Storagebox hardware have been rented for that purpose.
1736579
- 1 x Dedicated Root Server "Server Auction"
- Intel Xeon E3-1275v5
- 2x SSD M.2 NVMe 512 GB
- 4x RAM 16384 MB DDR4 ECC
- NIC 1 Gbit Intel I219-LM
- Location: FSN1-DC1
- Rescue system (English)
- 1 x Primary IPv4