Difference between revisions of "Free Float"
(Created page with "Free Float is the amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. See als...") |
|||
Line 2: | Line 2: | ||
==Definition== | ==Definition== | ||
− | According to [[ | + | According to the [[PMI Lexicon of Project Management Terms]], |
:[[Free Float]]. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. See also total float, critical path, near-critical activity, and near-critical path. | :[[Free Float]]. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. See also total float, critical path, near-critical activity, and near-critical path. | ||
− | [[Category: | + | [[Category: Project Management]][[Category: Articles]] |
Latest revision as of 19:06, 3 July 2020
Free Float is the amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. See also total float, critical path, near-critical activity, and near-critical path.
Definition
According to the PMI Lexicon of Project Management Terms,
- Free Float. The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint. See also total float, critical path, near-critical activity, and near-critical path.