Difference between revisions of "Enterprise effort"

From CNM Wiki
Jump to: navigation, search
 
(7 intermediate revisions by the same user not shown)
Line 1: Line 1:
[[Enterprise effort]] (hereinafter, the ''Effort'') is a determined attempt or a set of attempts undertaken by individuals, groups, and/or organizations in order to create or support some [[enterprise]] and/or its [[process]]es and/or to create its [[product]]s and/or to contribute to their features.
+
[[Enterprise effort]] (hereinafter, the ''Effort'') is a determined attempt or a set of attempts undertaken by individuals, groups, and/or organizations in order to create or support some [[enterprise]] and/or its [[process]]es and/or to create its [[market exchangeable]]s and/or to contribute to their features.
  
  
Line 5: Line 5:
  
 
===Definitions===
 
===Definitions===
#[[Task]]. The lowest level of the ''Effort'' that
+
#[[Job task]]. The lowest level of the ''Effort'' that
#[[Activity]]. The ''Effort'' undertaken as part of a [[process]]. An activity shall have its own name and description; most often, they have one or more [[predecessor activity|predecessor activiti]]es and [[successor activity|successor activiti]]es. Planned activities may have their expected input resources, process assets, time frames, and costs; completed activities may have their actual data. Activities may be subdivided into [[task]]s.  
+
#[[Activity]]. The ''Effort'' undertaken as part of a [[process]]. An activity shall have its own name and description; most often, they have one or more [[predecessor activity|predecessor activiti]]es and [[successor activity|successor activiti]]es. Planned activities may have their expected input resources, process assets, time frames, and costs; completed activities may have their actual data. Activities may be subdivided into [[job task]]s.  
 
#[[Process]].
 
#[[Process]].
, [[project]] or [[operations]], and/or [[enterprise]]
+
#[[Project]].
 +
#[[Operations]].
 +
#[[Enterprise]].
 +
#[[Effort]]. The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration.
 +
#[[Level of effort]] (LOE). Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a period of time determined by the activities it supports.
  
*[[Effort]]. The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration.
+
==Related lectures==
*[[Level of effort]] (LOE). Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a period of time determined by the activities it supports.
+
*[[Effort Engineering Quarter]].  
  
==Curriculum==
+
[[Category: Septem Artes Administrativi]][[Category: Articles]]
[[Chief Execution Quarter]]
 

Latest revision as of 16:39, 5 May 2023

Enterprise effort (hereinafter, the Effort) is a determined attempt or a set of attempts undertaken by individuals, groups, and/or organizations in order to create or support some enterprise and/or its processes and/or to create its market exchangeables and/or to contribute to their features.


Level of enterprise effort

Definitions

  1. Job task. The lowest level of the Effort that
  2. Activity. The Effort undertaken as part of a process. An activity shall have its own name and description; most often, they have one or more predecessor activities and successor activities. Planned activities may have their expected input resources, process assets, time frames, and costs; completed activities may have their actual data. Activities may be subdivided into job tasks.
  3. Process.
  4. Project.
  5. Operations.
  6. Enterprise.
  7. Effort. The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration.
  8. Level of effort (LOE). Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a period of time determined by the activities it supports.