Difference between revisions of "Resource Smoothing"
(Created page with "Resource Optimization Technique is a technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply. See also re...") |
|||
Line 1: | Line 1: | ||
− | [[Resource | + | [[Resource Smoothing]] is a resource optimization technique in which free and total float are used without affecting the critical path. See also resource leveling and resource optimization technique. |
+ | |||
==Definition== | ==Definition== | ||
According to the [[PMI Lexicon of Project Management Terms]], | According to the [[PMI Lexicon of Project Management Terms]], | ||
− | :[[Resource | + | :[[Resource Smoothing]]. A resource optimization technique in which free and total float are used without affecting the critical path. See also resource leveling and resource optimization technique. |
+ | |||
[[Category: Project Management]][[Category: Articles]] | [[Category: Project Management]][[Category: Articles]] |
Latest revision as of 14:54, 4 July 2020
Resource Smoothing is a resource optimization technique in which free and total float are used without affecting the critical path. See also resource leveling and resource optimization technique.
Definition
According to the PMI Lexicon of Project Management Terms,
- Resource Smoothing. A resource optimization technique in which free and total float are used without affecting the critical path. See also resource leveling and resource optimization technique.