Difference between revisions of "Enterprise effort"
(→Level of enterprise effort) |
|||
Line 3: | Line 3: | ||
==Level of enterprise effort== | ==Level of enterprise effort== | ||
+ | |||
+ | ===Definitions=== | ||
#[[Task]]. The lowest level of the ''Effort'' that | #[[Task]]. The lowest level of the ''Effort'' that | ||
− | , [[activity]], [[ | + | #[[Activity]]. The ''Effort'' undertaken as part of a [[process]]. An activity shall have its own name and description; most often, they have one or more [[predecessor activity|predecessor activiti]]es and [[successor activity|successor activiti]]es. Planned activities may have their expected input resources, process assets, time frames, and costs; completed activities may have their actual data. Activities may be subdivided into [[task]]s. |
+ | #[[Process]]. | ||
+ | , [[project]] or [[operations]], and/or [[enterprise]] | ||
*[[Effort]]. The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration. | *[[Effort]]. The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration. |
Revision as of 02:00, 12 April 2018
Enterprise effort (hereinafter, the Effort) is a determined attempt or a set of attempts undertaken in order to create outputs from a task, activity, process, project or operations, and/or enterprise.
Level of enterprise effort
Definitions
- Task. The lowest level of the Effort that
- Activity. The Effort undertaken as part of a process. An activity shall have its own name and description; most often, they have one or more predecessor activities and successor activities. Planned activities may have their expected input resources, process assets, time frames, and costs; completed activities may have their actual data. Activities may be subdivided into tasks.
- Process.
, project or operations, and/or enterprise
- Effort. The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration.
- Level of effort (LOE). Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a period of time determined by the activities it supports.