Estimate to Complete (ETC) is the expected cost to finish all the remaining project work. See also actual cost (AC), budget at completion (BAC), earned value (EV), estimate at completion (EAC) and planned value (PV).

Definition

According to the PMI Lexicon of Project Management Terms,

Estimate to Complete (ETC). The expected cost to finish all the remaining project work. See also actual cost (AC), budget at completion (BAC), earned value (EV), estimate at completion (EAC) and planned value (PV).