Logical relationship

From CNM Wiki
Revision as of 01:24, 21 November 2018 by Gary (talk | contribs) (Created page with "400px|thumb|right|[[Logical relationships]]Logical relationship (hereinafter, the '''Relationship'') is a dependency between two project activities...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Logical relationship (hereinafter, the 'Relationship) is a dependency between two project activities, or between a project activity and a milestone. The four possible types of logical relationships exist.

Types

  • Finish-to-start — the initiation of work of the successor depends upon the completion of work of the predecessor.
  • Finish-to-finish — the completion of the work of the successor cannot finish until the completion of work of the predecessor.
  • Start-to-start — the initiation of work of the successor depends upon the initiation of the work of the predecessor.
  • Start-to-finish — the completion of the successor is dependent upon the initiation of the predecessor.

Related coursework