Weighted Milestone Method

From CNM Wiki
Jump to: navigation, search

Weighted Milestone Method is a method of estimating earned value in which the budget value of a work package is divided into measurable segments, each ending with a milestone that is assigned a weighted budget value. See also fixed formula method.

Definition

According to the PMI Lexicon of Project Management Terms,

Weighted Milestone Method. A method of estimating earned value in which the budget value of a work package is divided into measurable segments, each ending with a milestone that is assigned a weighted budget value. See also fixed formula method.